Amarillo Gold Updates Resource Model, Files Technical Report. Mara Rosa Project, Brazil

Original announcement by tmx on

Company
Amarillo Gold Corp
Ticker
AGC
Exchange
TSX
Region
Goias, Brazil
Primary commodity
Gold
Secondary commodities
None reported
Document categories
Resource update, Permitting
Extracted
2026-09-13 11:35:54 UTC

Analysis by Minestarters Atlas

Minestarters Atlas analysis

Summary

Amarillo Gold Corp has released a new NI 43-101 technical report for the Posse deposit at the Mara Rosa project in Brazil. The updated resource estimate shows 22.03 Mt at 1.71 g/t gold (M&I) and the company has obtained a Preliminary License (LP) for the project.

Reasoning: The update provides a new resource model for the Posse deposit with improved ounces in the measured category and a key permitting milestone (LP).

Positive factors

  • Resource improvement noted vs July release
  • Obtained LP (Preliminary License) permitting milestone
  • QP sign-off provided by independent consultant

Negative factors

  • Resource is not reserves and lacks demonstrated economic viability

Facts used in scoring: 3

Classification and evidence

NI 43-101 Compliantpositive

Resource estimate prepared in compliance with NI 43-101 (Canada) — high reporting standard.

Why it applies: The technical report is stated to be a 43-101 technical report.

Evidence · text

“43-101 technical report to support the new resource model”

QP/CP Signedpositive

Qualified Person (QP) or Competent Person (CP) named and signed off — a member of a recognized professional association (e.g., AusIMM, SME, AIG, P.Geo) with relevant experience.

Why it applies: Keith Whitehouse, an independent QP, has reviewed and approved the content.

Evidence · text

“He has reviewed and approved the content of this News Release.”

Cut-off Disclosedpositive

Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: The resource estimate was calculated at a 0.5 g/t cutoff.

Evidence · text

“calculated the new resource estimate at a 0.5 g/t cutoff”

Extracted facts

Stored fact records: 3. Some facts used in scoring do not have a stored record.

Resource Estimates (3)

measuredMara Rosa Project · goldTonnes: 8877000Grade: 1.98Grade Unit: g/tContained Metal: 563700Contained Unit: ozView all details
Link to this fact

Identity

Project
Mara Rosa Project
Commodity
gold
Region
brazil
Reported Region
Goias, Brazil
Ticker
AGC

Resource scope

Estimate type
resource
Reporting standards
ni_43_101
QP Signed
Yes
Qualified person names
Keith Whitehouse
Resource group id
resource:c67ee4cb06f067104820
Deposit or zone
Posse
Mining method
combined

Resource Data

Category
measured
Tonnes
8877000
Grade
1.98
Grade Unit
g/t
Contained Metal
563700
Contained Unit
oz
Cutoff Grade
0.5
Cutoff Unit
g/t

Lab

Laboratory
Australian Exploration Field Services Ltd

Review

Needs Review
No
Historical
No

Dates

Event date
2016-09-27T00:00:00.000Z

Reasoning: Measured resource provides the highest level of geological confidence.

Positive factors

  • High confidence category

Evidence · table

“1.98”

Context: 8,877,000

Tags used in scoring

Measured Resourcepositive

Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

Cut-off Disclosedpositive

Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff_grade is stated

QP/CP Signedpositive

Qualified Person (QP) or Competent Person (CP) named and signed off — a member of a recognized professional association (e.g., AusIMM, SME, AIG, P.Geo) with relevant experience.

Why it applies: qp_signed is true

NI 43-101 Compliantpositive

Resource estimate prepared in compliance with NI 43-101 (Canada) — high reporting standard.

Why it applies: reporting_standards includes ni_43_101

PFS-Supportingneutral

Resource estimate prepared to support a Pre-Feasibility Study — requires adequate M&I component.

Why it applies: the release names the study this estimate supports

DFS-Supportingneutral

Resource estimate prepared to support a Definitive Feasibility Study — requires high M&I confidence.

Why it applies: the release names the study this estimate supports

indicatedMara Rosa Project · goldTonnes: 13149000Grade: 1.53Grade Unit: g/tContained Metal: 646500Contained Unit: ozView all details
Link to this fact

Identity

Project
Mara Rosa Project
Commodity
gold
Region
brazil
Reported Region
Goias, Brazil
Ticker
AGC

Resource scope

Estimate type
resource
Reporting standards
ni_43_101
QP Signed
Yes
Qualified person names
Keith Whitehouse
Resource group id
resource:76e8c739b47c24d34fc0
Deposit or zone
Posse
Mining method
combined

Resource Data

Category
indicated
Tonnes
13149000
Grade
1.53
Grade Unit
g/t
Contained Metal
646500
Contained Unit
oz
Cutoff Grade
0.5
Cutoff Unit
g/t

Lab

Laboratory
Australian Exploration Field Services Ltd

Review

Needs Review
No
Historical
No

Dates

Event date
2016-09-27T00:00:00.000Z

Reasoning: Indicated resource provides reasonable geological confidence.

Positive factors

  • Reasonable geological confidence

Evidence · table

“1.53”

Context: 13,149,000

Tags used in scoring

Indicated Resourcepositive

Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

Cut-off Disclosedpositive

Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff_grade is stated

QP/CP Signedpositive

Qualified Person (QP) or Competent Person (CP) named and signed off — a member of a recognized professional association (e.g., AusIMM, SME, AIG, P.Geo) with relevant experience.

Why it applies: qp_signed is true

NI 43-101 Compliantpositive

Resource estimate prepared in compliance with NI 43-101 (Canada) — high reporting standard.

Why it applies: reporting_standards includes ni_43_101

PFS-Supportingneutral

Resource estimate prepared to support a Pre-Feasibility Study — requires adequate M&I component.

Why it applies: the release names the study this estimate supports

DFS-Supportingneutral

Resource estimate prepared to support a Definitive Feasibility Study — requires high M&I confidence.

Why it applies: the release names the study this estimate supports

inferredMara Rosa Project · goldTonnes: 7119000Grade: 1.26Grade Unit: g/tContained Metal: 287700Contained Unit: ozView all details
Link to this fact

Identity

Project
Mara Rosa Project
Commodity
gold
Region
brazil
Reported Region
Goias, Brazil
Ticker
AGC

Resource scope

Estimate type
resource
Reporting standards
ni_43_101
QP Signed
Yes
Qualified person names
Keith Whitehouse
Resource group id
resource:ea2945d22945573ba10f
Deposit or zone
Posse
Mining method
combined

Resource Data

Category
inferred
Tonnes
7119000
Grade
1.26
Grade Unit
g/t
Contained Metal
287700
Contained Unit
oz
Cutoff Grade
0.5
Cutoff Unit
g/t

Lab

Laboratory
Australian Exploration Field Services Ltd

Review

Needs Review
No
Historical
No

Dates

Event date
2016-09-27T00:00:00.000Z

Reasoning: Inferred resource has limited geological confidence.

Negative factors

  • Speculative category

Evidence · table

“1.26”

Context: 7,119,000

Tags used in scoring

Inferred Resourcenegative

Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

Cut-off Disclosedpositive

Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff_grade is stated

QP/CP Signedpositive

Qualified Person (QP) or Competent Person (CP) named and signed off — a member of a recognized professional association (e.g., AusIMM, SME, AIG, P.Geo) with relevant experience.

Why it applies: qp_signed is true

NI 43-101 Compliantpositive

Resource estimate prepared in compliance with NI 43-101 (Canada) — high reporting standard.

Why it applies: reporting_standards includes ni_43_101

PFS-Supportingneutral

Resource estimate prepared to support a Pre-Feasibility Study — requires adequate M&I component.

Why it applies: the release names the study this estimate supports

DFS-Supportingneutral

Resource estimate prepared to support a Definitive Feasibility Study — requires high M&I confidence.

Why it applies: the release names the study this estimate supports

How Atlas produces this analysis

Minestarters Atlas uses automated extraction to summarize mining announcements, identify reported measurements, and classify supporting evidence. Sentiment reflects the extracted narrative and classification rules; it is an interpretation, not a reported measurement. Evidence quotes and context are provided where available. Missing data, low-confidence results, and review flags indicate limitations. Check the original publisher announcement before relying on an interpretation.