# Giyani Announces Positive Definitive Feasibility Study Results for the K.Hill Battery-Grade Manganese Project in Botswana

Canonical Atlas analysis: https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc

Original source: https://money.tmx.com/en/quote/EMM/news/5142819406664579/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba

Publisher: tmx

Original announcement: 2026-05-28T10:55:00.000Z

Analysis by Minestarters Atlas

Atlas analysis published: Unknown date

Atlas analysis updated: Unknown date

- Company: Giyani Metals Corp.

- Ticker: EMM

- Exchange: TSX

- Region: Botswana

- Primary commodity: Manganese

- Secondary commodities: None reported

- Document categories: Resource update, Economic study

- Extracted: 2026-09-19 18:58:59 UTC

Narrative sentiment: 0.80 · Bullish

## Minestarters Atlas summary

Giyani Metals Corp. announced positive Definitive Feasibility Study \(DFS\) results for its K.Hill Battery-Grade Manganese Project in Botswana. The DFS outlines robust post-tax economics with an NPV of US$481 million and an IRR of 20.3%, supporting a 25-year mine life. The study also declares Mineral Reserves and details capital and operating costs for the production of battery-grade manganese products.

Reasoning: The document announces positive Definitive Feasibility Study results for the K.Hill Battery-Grade Manganese Project, demonstrating strong economic returns and supporting Mineral Reserve declaration. The study outlines a long mine life, robust capital estimates with contingency, and positions the company as a key supplier in the battery-grade manganese market. While the AACE class and engineering maturity indicate some remaining uncertainty, the overall results are highly positive for the project's development.

- Positive factor: The Definitive Feasibility Study \(DFS\) demonstrates strong post-tax economics with an NPV of US$481 million and an IRR of 20.3%.

- Positive factor: The project has a long life of 25 years, providing stability and long-term production.

- Positive factor: The DFS supports the declaration of Mineral Reserves, indicating a high level of confidence in the mine plan.

- Positive factor: The study includes a P80 contingency of 11.5%, reflecting a robust capital cost estimate.

- Positive factor: The project aims to produce battery-grade manganese products \(HPMSM and HPMO\) for a structurally tightening market, offering strategic supply diversification outside China.

- Negative factor: The AACE Class 3 estimate has a wide accuracy range of -10% to +25%, indicating some remaining cost uncertainty.

- Negative factor: The study's engineering definition maturity is approximately 10% – 40%, which is at the lower end for a DFS.

- Negative factor: Inferred resources of 4.4 million tonnes are excluded from the LOP, which could be seen as conservative but also means they are not yet part of the economic model.

- Negative factor: The effective date of the Mineral Resource Estimate is October 20, 2025, which is slightly older than the DFS base date.

Low confidence — this extraction should be reviewed alongside the original source.

Facts used in scoring: 8

## Classification and evidence

**DFS Bankable**

Polarity: positive

Definition: AACE Class 2-1 study complete and within the staleness window.

Why it applies: The document announces the results of a Definitive Feasibility Study \(DFS\) for the K.Hill Battery-Grade Manganese Project.

Evidence · text

> Giyani Announces Positive Definitive Feasibility Study Results for the K.Hill Battery-Grade Manganese Project in Botswana

**High IRR**

Polarity: positive

Definition: Post-tax real unlevered IRR in the strong tier or better.

Why it applies: The post-tax IRR is 20.3%, which is above the strong tier threshold of 15% for a greenfield project.

Evidence · table

> 20.3

Context: IRR

**Fast Payback**

Polarity: positive

Definition: Payback in the strong tier or better, on the required basis.

Why it applies: The post-tax payback period is 4.8 years, which is within the moderate tier threshold of 5 years.

Evidence · table

> 4.8

Context: Payback from start of processing, undiscounted

**Long Reserve Life**

Polarity: positive

Definition: Reserve life index in the top tier of the single ladder.

Why it applies: The project has a life of 25 years, which is above the long-life threshold of 20 years.

Evidence · table

> 25

Context: Life of the Project

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: The news release states that the scientific and technical information has been reviewed and approved by Qualified Persons \(QPs\) as defined under NI 43-101.

Evidence · text

> The scientific and technical information in this news release has been reviewed and approved by the following Qualified Persons \("QPs"\) as defined under NI 43-101

**JORC Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with JORC Code \(Australia\) — high reporting standard.

Why it applies: The Mineral Reserve estimate was reported in accordance with the guidelines of the National Instrument 43-101, which is a high reporting standard.

Evidence · text

> The DFS supports the declaration of a Mineral Reserve estimate at K.Hill, prepared in accordance with CIM Definition Standards \(2014\) and reported under NI 43-101.

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: The Mineral Reserve estimate was reported in accordance with the guidelines of the National Instrument 43-101, which is a high reporting standard.

Evidence · text

> The DFS supports the declaration of a Mineral Reserve estimate at K.Hill, prepared in accordance with CIM Definition Standards \(2014\) and reported under NI 43-101.

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: The Mineral Resource Statement includes 4.4 Mt of Inferred resources.

Evidence · table

> 4.4

Context: Inferred

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: A current resource fact retains the disclosed cut-off grade

## Extracted facts

Stored fact records: 7. Some facts used in scoring do not have a stored record.

## Resource Estimates (7)

### proven

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-1)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: reserve
- Effective date: 2026-04-30T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Jaco Lotheringen
- Resource group id: resource:d389fc8034b69088f996
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: proven
- Tonnes: 1920000
- Grade: 14.5
- Grade Unit: % Mn
- Cutoff Grade: 8.8
- Cutoff Unit: %

#### Prior Estimate

- Resource Date: 2026-04-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: The declaration of Proven Mineral Reserves is a significant de-risking event for the project, indicating a high level of confidence in the economic viability of this portion of the resource.

- Positive factor: Declaration of Proven Reserves indicates a high level of geological and economic confidence.

- Positive factor: High manganese grade of 14.5% Mn for the Proven category.

Evidence · table

> 1.92

Context: Proven

#### Tags used in scoring

**Proven Reserve**

Polarity: positive

Definition: Measured Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "proven"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### probable

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-2)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: reserve
- Effective date: 2026-04-30T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Jaco Lotheringen
- Resource group id: resource:d3afba080bc8b0d1d599
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: probable
- Tonnes: 3420000
- Grade: 10.6
- Grade Unit: % Mn
- Cutoff Grade: 8.8
- Cutoff Unit: %

#### Prior Estimate

- Resource Date: 2026-04-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: The Probable Mineral Reserve contributes substantially to the project's mine life and economic model, providing a solid foundation for future development.

- Positive factor: Declaration of Probable Reserves adds to the overall confidence in the project's economic viability.

- Positive factor: Significant tonnage in the Probable category \(3.42 Mt\).

Evidence · table

> 3.42

Context: Probable

#### Tags used in scoring

**Probable Reserve**

Polarity: positive

Definition: Indicated Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "probable"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### proven

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-3)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: reserve
- Effective date: 2026-04-30T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Jaco Lotheringen
- Resource group id: resource:37bec5614e8e430438dd
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: proven
- Tonnes: 5350000
- Grade: 12
- Grade Unit: % Mn
- Cutoff Grade: 8.8
- Cutoff Unit: %

#### Prior Estimate

- Resource Date: 2026-04-30

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: The total Mineral Reserve estimate underpins the economic viability demonstrated in the DFS, confirming sufficient material for the planned operation.

- Positive factor: The combined Proven + Probable Reserves of 5.35 Mt provide a robust foundation for the project's 25-year mine life.

- Positive factor: The average grade of 12.0% Mn for the combined reserves is strong.

Evidence · table

> 5.35

Context: Proven + Probable

#### Tags used in scoring

**Proven Reserve**

Polarity: positive

Definition: Measured Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "proven"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### measured

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-4)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: resource
- Effective date: 2025-10-20T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Malcolm Titley
- Resource group id: resource:edf5a08ce381e5c1b238
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: measured
- Tonnes: 1800000
- Grade: 20.8
- Grade Unit: % MnO
- Cutoff Grade: 8.8
- Cutoff Unit: % MnO

#### Prior Estimate

- Resource Date: 2025-10-20

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: The Measured Mineral Resource provides a strong foundation for the project, indicating a high degree of confidence in the geological model and grade continuity.

- Positive factor: Measured Resources represent the highest level of geological confidence.

- Positive factor: High grade of 20.8% MnO for the Measured category.

Evidence · table

> 1.8

Context: Measured

#### Tags used in scoring

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### indicated

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-5)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: resource
- Effective date: 2025-10-20T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Malcolm Titley
- Resource group id: resource:d7c982abf528db068ea5
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: indicated
- Tonnes: 4200000
- Grade: 14.7
- Grade Unit: % MnO
- Cutoff Grade: 8.8
- Cutoff Unit: % MnO

#### Prior Estimate

- Resource Date: 2025-10-20

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: The Indicated Mineral Resource adds substantial tonnage to the project's resource base, contributing to the overall confidence in the deposit.

- Positive factor: Indicated Resources provide reasonable geological confidence and can support economic studies.

- Positive factor: Significant tonnage in the Indicated category \(4.2 Mt\).

Evidence · table

> 4.2

Context: Indicated

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### measured

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-6)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: resource
- Effective date: 2025-10-20T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Malcolm Titley
- Resource group id: resource:e94246c6c7618879c261
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: measured
- Tonnes: 6000000
- Grade: 16.5
- Grade Unit: % MnO
- Cutoff Grade: 8.8
- Cutoff Unit: % MnO

#### Prior Estimate

- Resource Date: 2025-10-20

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: The substantial Measured and Indicated Mineral Resource demonstrates a high level of geological confidence, forming a strong basis for the project's economic evaluation and future development.

- Positive factor: The combined Measured + Indicated Resources of 6.0 Mt provide a strong and confident resource base for the project.

- Positive factor: The average grade of 16.5% MnO for M+I is robust.

Evidence · table

> 6.0

Context: Measured + Indicated

#### Tags used in scoring

**Measured Resource**

Polarity: positive

Definition: Highest confidence category — tonnage, grade, shape well-established from closely-spaced drilling. Basis for Proven Reserves.

Why it applies: category is "measured"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### inferred

[Link to this fact](https://atlas-extractions.minestarters.com/news/giyani-announces-positive-definitive-feasibility-study-results-for-the-k-hill-ba--bbdf5526-8c02-44ea-a094-703846fedbdc#fact-resource-facts-7)

K.Hill Battery-Grade Manganese Project · manganese

#### Identity

- Project: K.Hill Battery-Grade Manganese Project
- Commodity: manganese
- Region: botswana
- Reported Region: Botswana
- Ticker: EMM

#### Resource scope

- Estimate type: resource
- Effective date: 2025-10-20T00:00:00.000Z
- Reporting standards: ni\_43\_101
- QP Signed: Yes
- Qualified person names: Malcolm Titley
- Resource group id: resource:ca9e05d6917fd940852b
- Deposit or zone: K.Hill
- Mining method: open\_pit
- Ownership percent: 100 %

#### Resource Data

- Category: inferred
- Tonnes: 4400000
- Grade: 14.7
- Grade Unit: % MnO
- Cutoff Grade: 8.8
- Cutoff Unit: % MnO

#### Prior Estimate

- Resource Date: 2025-10-20

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-05-28T00:00:00.000Z

Reasoning: While Inferred resources represent future potential, their speculative nature and exclusion from the current mine plan mean they do not contribute to the immediate economic viability of the project, though they offer upside.

- Positive factor: Inferred resources provide geological upside and potential for future conversion to higher confidence categories.

- Positive factor: The document explicitly states that Inferred resources are excluded from the LOP, indicating a conservative approach to the DFS.

- Negative factor: Inferred resources are speculative and cannot support economic studies alone.

- Negative factor: The exclusion of Inferred resources from the LOP means they do not currently contribute to the project's economic model.

Evidence · table

> 4.4

Context: Inferred

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Disclosed**

Polarity: positive

Definition: Cut-off grade used for resource reporting is clearly stated, enabling like-for-like comparison.

Why it applies: cutoff\_grade is stated

**QP/CP Signed**

Polarity: positive

Definition: Qualified Person \(QP\) or Competent Person \(CP\) named and signed off — a member of a recognized professional association \(e.g., AusIMM, SME, AIG, P.Geo\) with relevant experience.

Why it applies: qp\_signed is true

**NI 43-101 Compliant**

Polarity: positive

Definition: Resource estimate prepared in compliance with NI 43-101 \(Canada\) — high reporting standard.

Why it applies: reporting\_standards includes ni\_43\_101

**No Contained Metal**

Polarity: negative

Definition: Tonnage and grade reported but contained metal not calculated or disclosed — incomplete reporting.

Why it applies: contained\_metal was not reported

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

## How Atlas produces this analysis

Minestarters Atlas uses automated extraction to summarize mining announcements, identify reported measurements, and classify supporting evidence. Sentiment reflects the extracted narrative and classification rules; it is an interpretation, not a reported measurement. Evidence quotes and context are provided where available. Missing data, low-confidence results, and review flags indicate limitations. Check the original publisher announcement before relying on an interpretation.