# I-80’s Granite Creek resources triple, costs jump

Canonical Atlas analysis: https://atlas-extractions.minestarters.com/news/i-80-s-granite-creek-resources-triple-costs-jump--59de6987-96f8-4a26-9bc0-6a76c91b5270

Original source: https://www.northernminer.com/news/i-80s-granite-creek-resources-triple-costs-jump/1003895031/

Publisher: northernminer

Original announcement: 2026-09-22T14:37:44.000Z

Analysis by Minestarters Atlas

Atlas analysis published: Unknown date

Atlas analysis updated: Unknown date

- Company: i-80 Gold

- Ticker: IAU

- Exchange: Unavailable

- Region: Nevada

- Primary commodity: Gold

- Secondary commodities: None reported

- Document categories: Resource update, Economic study

- Extracted: 2026-09-22 14:49:29 UTC

Narrative sentiment: 0.10 · Bullish

## Minestarters Atlas summary

i-80 Gold has released a new feasibility study for the Granite Creek underground mine in Nevada, reporting a 229% increase in measured and indicated resources to 859,500 oz and the establishment of 556,500 oz of initial reserves. However, the study highlights a significant increase in life-of-mine AISC to $2,273/oz, up from $1,597/oz in the previous PEA.

Reasoning: The announcement delivers a major resource expansion and reserve establishment via a new feasibility study, but the economic profile is tempered by a significant jump in life-of-mine AISC.

- Positive factor: Significant resource growth \(229% increase in M&amp;I\)

- Positive factor: Establishment of initial reserves

- Positive factor: Improved metallurgical recovery \(87% vs 78%\)

- Positive factor: Expansion of mineralized footprint

- Negative factor: Sharply higher AISC \($2,273 vs $1,597 in PEA\)

- Negative factor: NPV sensitivity shows value erosion at higher gold prices compared to prior study

- Negative factor: Elevated costs weighting the economics

Facts used in scoring: 3

## Classification and evidence

**PFS Complete**

Polarity: positive

Definition: AACE Class 3 study complete.

Why it applies: The document describes a new feasibility study which, in the context of the project stage, serves as the primary economic update.

Evidence · text

> a new feasibility study also shows sharply higher costs than last year’s preliminary assessment

**Category Upgrade**

Polarity: positive

Definition: Resource confidence improved — Inferred upgraded to Indicated, or Indicated to Measured. De-risking signal.

Why it applies: The study establishes initial reserves and lifts measured and indicated resources significantly.

Evidence · text

> It also establishes initial reserves of 556,500 oz. and lifts measured and indicated resources 229% to 859,500 ounces.

**Tonnage Growth**

Polarity: positive

Definition: Tonnage increase reaching the strong tier vs prior estimate, with grade maintained or improved.

Why it applies: Measured and indicated resources increased by 229% compared to the previous PEA.

Evidence · text

> lifts measured and indicated resources 229% to 859,500 ounces

**Grade Decline**

Polarity: negative

Definition: Average grade fell below the red-flag bound vs prior estimate — deposit economics worsening. May indicate high-grading in early drilling.

Why it applies: While not explicitly stated as a decline, the massive tonnage growth relative to metal growth suggests dilution or lower grade expansion, though the headline grade remains high.

Evidence · text

> lifts measured and indicated resources 229% to 859,500 ounces

## Extracted facts

Stored fact records: 3. Some facts used in scoring do not have a stored record.

## Resource Estimates (3)

### probable

[Link to this fact](https://atlas-extractions.minestarters.com/news/i-80-s-granite-creek-resources-triple-costs-jump--59de6987-96f8-4a26-9bc0-6a76c91b5270#fact-resource-facts-0)

Granite Creek · gold

#### Identity

- Project: Granite Creek
- Commodity: gold
- Region: usa\_nv
- Reported Region: Nevada
- Ticker: IAU

#### Resource scope

- Estimate type: reserve
- Resource group id: resource:469f995a576a3676ad2e
- Mining method: combined

#### Resource Data

- Category: probable
- Tonnes: 2200000
- Grade: 7.87
- Grade Unit: g/t
- Contained Metal: 556500
- Contained Unit: oz

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-09-22T00:00:00.000Z

Reasoning: First formal reserve declaration for the project.

- Positive factor: Establishes initial reserves

Evidence · text

> The study establishes an initial 2.2 million proven and probable tonnes grading 7.87 grams gold per tonne for 556,500 oz. contained gold.

#### Tags used in scoring

**Probable Reserve**

Polarity: positive

Definition: Indicated Resource with demonstrated economic viability after applying modifying factors.

Why it applies: category is "probable"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**No QP/CP Disclosure**

Polarity: negative

Definition: No Qualified Person or Competent Person named — lower credibility for the estimate. A QP/CP should be a member of a recognized professional association with relevant experience.

Why it applies: no Qualified or Competent Person is named anywhere in the release

**PEA-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Preliminary Economic Assessment — early-stage study.

Why it applies: the release names the study this estimate supports

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### indicated

[Link to this fact](https://atlas-extractions.minestarters.com/news/i-80-s-granite-creek-resources-triple-costs-jump--59de6987-96f8-4a26-9bc0-6a76c91b5270#fact-resource-facts-1)

Granite Creek · gold

#### Identity

- Project: Granite Creek
- Commodity: gold
- Region: usa\_nv
- Reported Region: Nevada
- Ticker: IAU

#### Resource scope

- Estimate type: resource
- Resource group id: resource:cbd567dd6c98d0618cdf
- Mining method: combined

#### Resource Data

- Category: indicated
- Tonnes: 3730000
- Grade: 7.17
- Grade Unit: g/t
- Contained Metal: 859500
- Contained Unit: oz

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-09-22T00:00:00.000Z

Reasoning: Significant increase in M&amp;I resource scale.

- Positive factor: Substantial resource growth

Evidence · text

> Granite Creek now hosts 3.73 million measured and indicated tonnes grading 7.17 grams gold per tonne for 859,500 oz., up 229% from the PEA

#### Tags used in scoring

**Indicated Resource**

Polarity: positive

Definition: Reasonable geological confidence based on adequate drilling; continuity can be assumed. Basis for Probable Reserves.

Why it applies: category is "indicated"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**No QP/CP Disclosure**

Polarity: negative

Definition: No Qualified Person or Competent Person named — lower credibility for the estimate. A QP/CP should be a member of a recognized professional association with relevant experience.

Why it applies: no Qualified or Competent Person is named anywhere in the release

**PEA-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Preliminary Economic Assessment — early-stage study.

Why it applies: the release names the study this estimate supports

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

### inferred

[Link to this fact](https://atlas-extractions.minestarters.com/news/i-80-s-granite-creek-resources-triple-costs-jump--59de6987-96f8-4a26-9bc0-6a76c91b5270#fact-resource-facts-2)

Granite Creek · gold

#### Identity

- Project: Granite Creek
- Commodity: gold
- Region: usa\_nv
- Reported Region: Nevada
- Ticker: IAU

#### Resource scope

- Estimate type: resource
- Resource group id: resource:fd35a0011067b49a6251
- Mining method: combined

#### Resource Data

- Category: inferred
- Tonnes: 893000
- Grade: 7.06
- Grade Unit: g/t
- Contained Metal: 202800
- Contained Unit: oz

#### Review

- Needs Review: No
- Historical: No

#### Dates

- Event date: 2026-09-22T00:00:00.000Z

Reasoning: Inferred resource is present but smaller than before due to conversion to higher confidence categories.

- Positive factor: Maintains high grade in inferred category

- Negative factor: Inferred ounces declined due to conversion

Evidence · text

> while 893,000 inferred tonnes grade 7.06 grams for 202,800 ounces.

#### Tags used in scoring

**Inferred Resource**

Polarity: negative

Definition: Speculative category — limited drilling, geological continuity assumed but not confirmed. Cannot support economic studies alone.

Why it applies: category is "inferred"

**Cut-off Undisclosed**

Polarity: negative

Definition: High-grade interval reported without stating the cut-off grade used for compositing.

Why it applies: no cutoff\_grade was stated

**No QP/CP Disclosure**

Polarity: negative

Definition: No Qualified Person or Competent Person named — lower credibility for the estimate. A QP/CP should be a member of a recognized professional association with relevant experience.

Why it applies: no Qualified or Competent Person is named anywhere in the release

**PEA-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Preliminary Economic Assessment — early-stage study.

Why it applies: the release names the study this estimate supports

**DFS-Supporting**

Polarity: neutral

Definition: Resource estimate prepared to support a Definitive Feasibility Study — requires high M&amp;I confidence.

Why it applies: the release names the study this estimate supports

## How Atlas produces this analysis

Minestarters Atlas uses automated extraction to summarize mining announcements, identify reported measurements, and classify supporting evidence. Sentiment reflects the extracted narrative and classification rules; it is an interpretation, not a reported measurement. Evidence quotes and context are provided where available. Missing data, low-confidence results, and review flags indicate limitations. Check the original publisher announcement before relying on an interpretation.