Allied Gold Energizes Power Line, Feeds First Ore to the Crushing Circuit as the Kurmuk Mine Progresses Toward Completion of Commissioning and Transitions to Operations
Allied Gold has achieved a major milestone at the Kurmuk Mine in Ethiopia with the successful energization of the electrical grid connection and the feeding of first ore into the crushing circuit. The company provided production guidance of 240,000 to 270,000 ounces for the first full year and noted a 2.7 million ounce Proven and Probable reserve base.